Monitoring Framework
Key Performance Indicators
Panuco Project Permitting Status (MIA Approval) QuarterlyTarget: Approval of Environmental Impact Assessment (MIA)
Panuco Project Construction Progress QuarterlyTarget: First silver production in H2 2027
Annual Silver Equivalent (AgEq) Production Profile AnnuallyTarget: 17.4 Moz AgEq average (20.1 Moz AgEq in Years 1-5)
Watch Items
- MIA Environmental Permit ApprovalTrigger: Delay beyond Q3 2026Action: Re-evaluate the H2 2027 first-pour timeline and adjust capital expenditure burn rate.
- Sinaloa Regional Security and On-Site OperationsTrigger: Escalation of local security incidents or operational suspensionsAction: Review security protocols, engage with local government relations, and assess impact on development schedule.
- Equipment Manufacturing and Delivery Lead TimesTrigger: Delays in FLSmidth engineering or manufacturing milestones under the Equipment Supply AgreementAction: Enforce contract schedule contingencies and coordinate with technical services team to optimize site preparation.