Alamos Gold Inc Dossier
Outlook & Key Dates
Estimates, guidance, catalysts, and upcoming events
Analyst Estimates Learn more →
5-Yr Fwd EPS Growth
38.2%projected annual EPS growth
Analyst Coverage
4analysts covering
FY Revenue (est.)
$2.4Bnext fiscal year
FY EPS (est.)
$2.30next fiscal year
Reporting Calendar
| Event | Expected Date |
|---|---|
| Q3 2026 Earnings Release | 28 Oct 2026 |
Monitoring Framework
Key Performance Indicators
Consolidated Gold Production Quarterly123.9KTarget: 570,000 to 650,000 ounces (Full Year 2026 original guidance, currently expected to fall below the low end)
All-In Sustaining Costs (AISC) Quarterly1.9KTarget: $1,500 to $1,600 per ounce (Full Year 2026 original guidance, currently expected to exceed)
Average Realized Gold Price Quarterly4.8KTarget: Market spot price dependent
Young-Davidson Underground Mining Rate Daily5KTarget: 8,000 tonnes per day (original guidance, revised to ~5,000 tpd for remainder of 2026)
Watch Items
- Young-Davidson Seismic Activity and Ground Support OptimizationTrigger: Mining rates falling below 5,000 tonnes per day or further infrastructure damageAction: Review geotechnical sequence, implement additional ground support measures, and adjust mine sequencing to mitigate seismicity.
- Island Gold Phase 3+ Shaft Expansion CommissioningTrigger: Delays in commissioning beyond early 2027Action: Monitor shaft bottom infrastructure construction progress through the second half of 2026 to ensure timely transition from truck hauling to shaft hoisting.
- Magino Mill Throughput ExpansionTrigger: Throughput failing to sustain 10,000 tonnes per day by Q3 2026 or delays in the 20,000 tpd expansion by early 2028Action: Track construction and exterior cladding of the new mill building and monitor daily mill throughput optimization.
Research as of 2 Sep 2026